Dwan-3-12-20

Ann – The interior finish carpenters are continuing with installing doors, window sills, and trim.  The exterior finish carpenters have framed the north deck, and are finishing up the siding and trim.  The cabinet installers have finished installing the Den/Game Room entertainment center, and are finishing up the Kitchen and Master Suite cabinets.  The Office, […]

Dwan-3-5-20

Ann – The interior trim carpenters continued on with the interior doors and trim in the Master wing this week, and will be heading back to the downstairs bedrooms next week.  The tile crew has been working in the downstairs baths and powder room, and also started the floor tile in the Pantry.  They will […]

Dwan-2-27-20

Ann – The interior trim carpenters have installed all of the rafter timbers in the Kitchen and Dining Room area, and then taken them down while they wait for the ridge beam wrap to be corrected – it was sent 1/2″ short in height.  The carpenters have moved on to the Living Room, and have […]

Dwan-2-20-20

Ann – The drywall finishers will be done with the main level today, and the painters will be starting on Monday with the ceilings and 1st coat on the walls.  The drywall finishers will be starting tape and texture on the areas in the basement that were formerly barn wood today.  The int. trim carpenters […]

Dwan-2-13-20

Ann – The trim carpenters are installing doors in the basement, and interior trim.  The drywall crew is finishing up the tape and texture in the Office, Kitchen, Pantry, Entry, Powder Room and Mud Room on the main level, and will have that area done tomorrow.  They will then work on the rest of the […]

Dwan-2-6-20

Ann – The drywall is progressing nicely, now that we seem to be keeping our workers onsite!  They have finished hanging the main level, and are hanging the basement areas that were formerly barn wood, and then will move to the Garage.  The drywall finishers are starting in the Office and Kitchen areas, and will […]

Dwan-1-31-20

Ann – The carpenters continued on the ext. siding this week, cutting the exterior beam ends, and setting the man-door at the Garage.  The trim carpenters were onsite for a few days, and installed the window sills in the Den/Game Room.  The interior trim arrived, and as soon as the interior doors arrive next Tuesday, […]

Dwan-1-23-20

Ann – The masons have finished the stone veneer on the retaining wall, and just have the cap to install. There will be a small area of stone above the basement window that will be installed after the deck ledger and flashing are installed.  They will be moving into the basement to install the fireplace […]

Dwan-1-16-20

Ann – Finally got the drywall delivered this afternoon, and the hangers will start tomorrow.  The painter has the paint schedule, and is putting the first coat of paint over the primed drywall in the basement.  The masons are finishing up the retaining wall stone veneer in the area that they have tented (75% of […]

Dwan-1-10-20

Ann – The spray foam insulation finished up this week, and the sound batt insulation will be installed today.  They should get most of it installed today, and will work Saturday to finish up.  We have an insulation inspection scheduled for Monday morning.  The drywall for the main level will be stocked on Monday morning, […]

Dwan-1-3-20

Ann – Happy New Year to all!  Most of the crews kept working through and around the holidays, so progress was made over the last 2 weeks.  The basement is drywalled, taped and finished, ready for paint.  The insulator is working on the main level, and sprayed the Office, Kitchen, and Dining Room today, while […]

Dwan-12-19-19

Ann – We passed the insulation inspection in the basement on Monday morning, and the drywall crew will have the basement drywall installed by this coming Monday morning, when we have a drywall inspection scheduled. The electricians passed their rough-in inspection on Wednesday afternoon, and the insulator started spraying the ext. walls and roof on […]

Dwan-12-12-19

Ann – The masons finished up the chimney stone work, and have set up and are starting on the retaining wall.  They also installed the missing fire brick on the sides of both fireplaces, and I let Jeff Morris know he can come back to measure for the fireplace doors/surround.  The HVAC crew has installed […]

Dwan-12-5-19

Ann – The insulators installed the spray foam insulation in the basement exterior walls today!  They finally got their electrical problem solved on their new truck, and got a lot done today.  The mason’s are done with the stone veneer on the chimney, and are setting the clay flue liners at the top that combine […]

Dwan-11-21-19

Ann – The carpenters finished the soffit this week, and have been finishing up the pocket door framing and recesses for the medicine cabinets.  The roofers are onsite, and have installed the membrane on the garage roof, and will be working on the flat entry roof tomorrow.  The floor heat crew from Synergy have finished […]

Dwan-11-14-19

Ann – The carpenters have one more window to set in the basement, and then the last remaining opening to fill is the front door.  The last of the foundation was poured late last week, so the carpenters were able to finish the floor and wall framing on the north side of the Kitchen, and […]

Dwan-11-7-19

Ann – The windows are being installed, and by the end of tomorrow, most of them will be in.  They look great!  The soffit crew is moving around the house, making good progress.  The plumbers passed rough-in inspection this week, and hopefully the electricians will do so next week, and then we can start insulating. […]

DWAN – 10-31-19

Ann – A cold, and busy, week.  The garage slab was poured on Monday, along with the footing for the crawlspace north wall.  Both areas were heated for 72 hours, and then we covered the garage slab this morning, just in time for the windows and ext. doors to be delivered.  The north wall of […]

Dwan-10-17-19

Ann – The carpenters are almost done putting down the Warmboard, and we should know tomorrow if we need to order more for the Mud Room, to add floor heat under the open cabinets.  Fascia is continuing to be installed, and we should be seeing the grey stainless steel screws early next week to replace […]

Dwan-10-10-19

Ann – The carpenters worked on starting the fascia this week, and installing the Warmboard.  They have been repairing the subfloor ahead of their Warmboard installation, and will be moving into the Living area next week.  The steel for the north deck was installed, and as soon as the last section of foundation wall gets […]

Dwan-10-3-19

Ann – The carpenters are finishing up int. framing details, and repairing the subfloor on the main level, ahead of starting the Warmboard-R installation.  They have finished framing in the floor and walls at the SW corner of the Kitchen/Office, now that the crawlspace wall below has been poured.  The fascia material arrived this week, […]

Dwan 9-6-19

Ron and all, We poured the large retaining wall today along with the footing at the old garage and one pier in the back for the deck.  Subs are working in basement still trying to piece the puzzle together.  Windows are set to deliver week of Oct 21.  Fascia and soffit are coming week after […]

Dwan-7-25-19

Ann – Great progress this week on the framing.  We set the 2 main ridge beams over the Kitchen/Dining/Entry areas on Tuesday, and rafters are going up.  The exterior wall framing at the front of the house is also underway.  The house will really take on it’s shape over the next few weeks.  The garage […]

Marino Farrell 6/28/19

Edward finished the oak paneling in the master this week – and the cabinet guys mostly finished up the remaining details. They will be back Monday for the final touch up. The plumber finished up all the faucets, sinks, shower components, and master tub, and turned the water on. The mechanical crew finalized and turned […]

Dwan-6-27-19

Ann – Continued good weather, and good progress.  The under slab utilities are in at the Office/Kitchen area (the old garage), and the slab is patched and ready for the floor to be framed over the slab to match the rest of the main floor elevation.  The Master wing roof framing is almost completed.  The […]

Marozzi-6-27-19

John & Marlene – The carpet installation started today in the upstairs bedrooms, with pieces being rough cut and placed in the bedrooms.  Pella came out with their VIP service, and placed all of the screens, installed the finish window cranks and covers, and adjusted their exterior doors.  The landscapers have installed the sod, sprinklers, […]

Marino Farrell 6/21/19

The landscapers worked on the entry walkway this week, and finished planting the grasses and moss on the south side of the house. They plan to wrap up the edges of the walkway once the driveway is paved. The plumbers completed quite a bit of fixture install, and prepped all the vanities  for when the […]

Dwan-6-20-19

Ann – The larger framing crew is really making progress, with the roof and wall demolition nearly complete, and the Master wing also nearly complete on the framing.  The plumbers installed the under slab plumbing in the Office wing today, and the electricians will run their conduits on Monday, as will the HVAC crew with […]

Marozzi-6-20-19

John & Marlene – The painters are finishing up the handrail caps, and we will install them early next week.  The electricians will be back next week to finish installing the fixtures we’ve received lately, and to trim out the floor outlets in the Living Room, now that the wood floor has been final coated. […]

Marozzi-6-14-19

John & Marlene – The home stretch!  The steel panels are installed on the chimney, and look great.  The electricians are trimmed out, except for a few outlets and the breakfast area chandelier, which they will take care of next week.  The painter’s finished the timbers at the front entry, and are essentially done.  We […]

Marino Farrell 6/13/19

The painters wrapped up their final coat on the living room on Monday, and have transitioned to working on painting/finishing the doors. The electricians have been back this week working on trim out. They wrapped up all the hard wire tasks in the crawlspace on Monday and spent the last three days finishing up most […]

Marino Farrell 6/7/19

Good progress this week on landscaping and cabinets. Woodland cabinetry has all the cabinets installed except for the entry closet and the floating shelves in the bedrooms They’ll be back in a week to finish those up. The painters have been chipping away at more prep, and painting the living room. They will keep working […]

Marozzi-6-7-19

John & Marlene – The steel panels are done on the chimney up to the roof.  We should have the section done above the roof by mid-next week.  The painters are on final touch-up.  The plumbers are done with trim-out, and the HVAC crew will do their trim-out next week.  The electricians are back onsite […]

Dwan-6-6-19

Ann – The steel beam that allowed for the north wall of the Master Bedroom to move to the north was installed Monday, along with the steel beam that will carry the roof framing over the expansion into the wedge shaped area between the Master Bedroom and the Garage.  This now allows the framers to […]

Marino Farrell 5/31/19

This was a short week with the holiday on Monday. The exterior crew finished up the last of the decking this week, as well as the deck fascia and the front entry steps. They installed the front door, and finished up the siding around it. The mechanical screen fence has been started as well. The […]

Marozzi-5-30-19

John & Marlene – With the improvement in the weather (it stopped snowing!), the painters are finishing up the front porch timbers, and putting a coat of sealer on the deck stairs that were installed too late last fall to seal.  They finished the garage, and are cleaning up and doing touch-up where needed.  Jesse […]

Marozzi-5-23-19

John & Marlene – The painters are finishing up the garage, and should be down to mostly touch-up next week.  The railings are installed, and I will have some railing wood caps mocked up for Chris to look at on Tuesday.  The latest info. that Jody gave me for the carpet got a thumbs up […]

Marino Farrell 5/23/19

Monday started out with 2″ of snow on the ground and we’ve been struggling to pull out of the downward wintery spiral every since. This week has been cold, windy, gray, rainy and snowy. Despite this, the crew working on the deck finished up all the deck boards and are installing deck fascia today and […]

Dwan-5-16-19

Ann – The carpenters finished framing the stairs this week, and today set the large Glulam beam into the ceiling above the Master Closet and Bedroom 112.  The shoring up of the basement wall between the Game Room and Mechanical/Storage 103 was completed yesterday when the concrete was poured.  The concrete slab was cut yesterday […]

Marozzi-5-16-19

John & Marlene – Appliances for the Kitchen and Wine Island were delivered and installed this week.  We have to change the plug for the wall oven, which the electricians will do on Monday.  Plumbers were back today to continue trim-out – setting toilets, faucets, and hooking up the gas to the range.  The cabinet […]