Marozzi-6-27-19

John & Marlene –

The carpet installation started today in the upstairs bedrooms, with pieces being rough cut and placed in the bedrooms.  Pella came out with their VIP service, and placed all of the screens, installed the finish window cranks and covers, and adjusted their exterior doors.  The landscapers have installed the sod, sprinklers, and plantings, and just have the hydroseed to do.  The cleaning crew has been working hard, and finished up the windows yesterday.  The HVAC crew worked on getting the AC going this week (don’t worry, we don’t have it on!), installing registers, setting thermostats, and adjusting the system.  The electricians are done, except for hanging the Dining Room fixture (working with John Bickner on that), the Office fixture, and the Master sconces when they return with switches installed on them.   – – – Dave

Custom Wordpress Web Design