Marino Farrell 5/23/19

Monday started out with 2″ of snow on the ground and we’ve been struggling to pull out of the downward wintery spiral every since. This week has been cold, windy, gray, rainy and snowy. Despite this, the crew working on the deck finished up all the deck boards and are installing deck fascia today and tomorrow. They also got a good start on the mechanical screen fence. The painters have been working to carefully prep and mask all the finishes, and are spraying primer on the west side of the house today. The cabinet guy has the kitchen island & sink wall, and master vanities installed. I met with Dan from DLS to go over countertops this morning, and he will have all the templates ready and submitted by the end of next week.