Ann –
The interior finish carpenters are continuing with installing doors, window sills, and trim. The exterior finish carpenters have framed the north deck, and are finishing up the siding and trim. The cabinet installers have finished installing the Den/Game Room entertainment center, and are finishing up the Kitchen and Master Suite cabinets. The Office, Master Bath, and Pantry cabinets arrived today, and will be going in next. The tile floor has been set in the Pantry, and just needs to be grouted. The electricians installed the heat cable in the Laundry today, and the tile crew has covered the cables, and are ready to set tile. The plumbers have been onsite this week, and have the shower valves set, and the drains and tub filler rough-in is done in the Master Bath. The roofers start on the standing metal seam roofing tomorrow. The forced air crew is working in the Mechanical Room and crawlspace, tying in the ductwork. – – – Dave