Ann –

We passed the insulation inspection in the basement on Monday morning, and the drywall crew will have the basement drywall installed by this coming Monday morning, when we have a drywall inspection scheduled. The electricians passed their rough-in inspection on Wednesday afternoon, and the insulator started spraying the ext. walls and roof on the main level today.  They should be done on the main level early next week, and then we can get inspected on that level, and start drywall.  The carpenters have been working on the exterior siding, and doing punch list framing and cleaning ahead of the insulators.  – – – Dave