Marozzi-6-20-19

John & Marlene –

The painters are finishing up the handrail caps, and we will install them early next week.  The electricians will be back next week to finish installing the fixtures we’ve received lately, and to trim out the floor outlets in the Living Room, now that the wood floor has been final coated.  The carpet will be installed starting Tuesday or Wednesday next week.  The landscapers are moving right along, with 11+ workers the last few days.  They should be done by mid-next week.  The cap will be installed on the chimney tomorrow, and then we can take the scaffolding down so the landscapers can finish in that area.  – – – Dave