Dwan-2-13-20

Ann –

The trim carpenters are installing doors in the basement, and interior trim.  The drywall crew is finishing up the tape and texture in the Office, Kitchen, Pantry, Entry, Powder Room and Mud Room on the main level, and will have that area done tomorrow.  They will then work on the rest of the main level drywall finish next week, while the finish carpenters start on the barn wood ceiling in the Office. Both the radiant floor heating crew and the forced air crew are setting equipment in the Mechanical Rooms.  The masons have tented the front entry, and will start on the stone work in that area next week.  The front door will be delivered next week, likely on Monday, weather allowing.  The first delivery of cabinets arrived yesterday, and the installer has already started to set cabinets.  The beam wraps also arrived this week.  The plumbers have the bath tubs (finally!), and are starting to install them.  – – – Dave