The framing crew installed the trusses for the ARU on Monday, and have been busy completing the remaining blocking, bracing, roof overbuild, and venting. They put the plywood on the roof, and will be back next week for the timbers. The excavator has installed the perimeter drain system around the basement foundation footings, and has tied it into the drain mat that lines the basement walls. He has partially backfilled the foundation walls, and will start prepping the basement for the concrete slab tomorrow. We have the electrician and plumbers scheduled to be on site on Monday and Tuesday to install their underslab components. The rest of the flooring system has been ordered, and the components should arrive soon.