We had a very productive week. The HVAC crew was on site to complete their trim out, installing all the grills and registers, the kitchen range hood, and the fireplace bricks and log set. The electrician completed installing the fixtures, and passed the final electrical inspection on Wednesday. We are now just waiting for the extensions for the island fixtures, the glass globe for the master fan, and the new lights for over the bar. The painters washed the upstairs deck and coated with water seal, and they are finishing final touch up on the inside. The carpenters are taking care of miscellaneous details on the interior and exterior. Everything is looking great.