Paint and trim continued upstairs this week. The painters finished primer in the great room/kitchen and have two coats of paint on the ceilings. The trim carpenters finished the guest wing and are working in the master wing on window trim. The drywall crew returned and hung sheetrock in the basement, and the county signed off on drywall this morning. The taping/texture crew will be there tomorrow. The carpenters set the timber mantel and metal wood box liner, and continue to work on subfloor when the painters aren’t in the way. The excavator is working on the rest of the terrace prep and will hopefully start work on the septic/leach field next week. The electrician was on site wrapping up some loose ends in the mechanical room, and starting to install light fixtures at the ARU. Fates flooring put the stain and first coat of finish on the guest house wood floors on Monday, and the carpenters are back in there hanging doors and working on baseboard and the remaining trim pieces.