Zimmerman 6/5/17

Sorry for the delay on this update. It was a very busy week, and wrapped up Friday with the concrete pour over the hydronic heat tubing. The west wing is now ready for subfloor and sheetrock. The insulation was inspected and passed on Tuesday. The oak trim package for the east wing of the main house arrived on Wendsday, and is stickered and acclimating in the exercise room and jr. master. Stone work on the exterior is coming along, and the fireplace chimney pipe was installed on the isokern in the great room. Window trim in the ARU is almost complete, and siding over there continues.

 

 