Zimmerman 6/30/16

Pierson was back on site on Monday to set points on the basement footings – this allows us to get a Certificate of Placement for the building, which is required by the county prior to pouring the concrete walls. The concrete crew mobilized their crane and have been busy setting the basement wall forms; they expect to be ready to pour the concrete on Tuesday. They are also simultaneously forming the crawlspace footings on the west side of the house and will pour those at the same time. The framing crew is making great progress on the ARU; after the excavator prepped the crawlspace on Tuesday, they jumped in and expect to start framing the walls tomorrow.

 