Zimmerman 4/13/17

We had almost a full week of nice weather, and the carpenters made good progress on the siding. The timber crew continues to work on interior timbers, and are also working on the knee braces on the outside. Sheetrock was delivered Monday, and the entire east wing (minus the garage) has been sheet rocked and is awaiting a nailing inspection. We should wrap that up tomorrow, and move on to tape and texture. Electricians, AV, Watchguard and HVAC continue their rough-in, and have finished the master wing and most of the great room. They should wrap up kitchen/mudroom area tomorrow, and be ready to move downstairs. The oak doors for the ARU were delivered today and are awaiting install in the coming weeks. Tile setter is ready to start over there as well.

 

 