The weather continues to alternate between winter and fall. Monday the crew was rained out, as heavy rain, cold and wind prevailed throughout the valley. Tuesday the crew was able to work for most of the day before getting rained out again – they completed the overbuild and roof sheeting on the east end of the house, and are working on framing over the breakfast room, as well as the fireplace framing. They set the master wing glulam beam on Wednesday afternoon, and are prepping for the crane to arrive and install the rest of the beams. The painter produced some cedar and timber samples, and it sounds like we’ll do one more round – hopefully this week – before deciding on a final shade.