Bob & Stacey –

Great week of progress.  Almost all of the windows and doors are set, soffit work is continuing, framing alterations for the subs. are continuing, and the masons are setting stone.  The electricians, plumbers, and HVAC crew have been roughing-in all week.  The excavator has been working on the front retaining wall excavation, and the concrete subs. are scheduled to start on Monday.  The cabinet maker will be measuring on Tues., verifying dimensions for the shop drawings.  I will be off starting Tuesday the 17th – Tuesday the 24th, heading back for my daughter’s graduation from NYU, and then to visit my mom for a few days.  I will be keeping in touch with the framer and all the subs., and Steve will be keeping things moving on the ground.  – – Dave