Morse-12-3-15

Bob & Stacey –

The framing crew is working on the roof over the Guest Master Suite, and should have that dried in next week.  They are also framing the lower roof over the Laundry and Mudroom area.  With most of the timbers onsite, and the steel timber connectors and decorative plates also here, they are starting the timbers that carry the 2nd floor.  Starting tomorrow, they are increasing the crew size.  They will be working on the remaining section of the 2nd floor deck, over the Dining Room and the Bridge to the Master Suite.  We received the first delivery of the upper roof trusses today, and will be seeing the rest of them next week, so we will be ready to frame the roof as the 2nd floor walls are completed.  The excavator is still working, taking the garage floor drains to daylight on the east side of the Garage today, and will likely finish up the backfill in front of the house next week if the weather allows.  – – – Dave