Harris 12/3/15

This week was a pretty cold one. The crew continued the horizontal and vertical siding, and made some headway on the remaining trim. They started the framing of the electrical closet after the slab was fully cured. I met briefly with the plumber on site about the remaining vent locations, sewer line and rough-in. Mike, the electrician, is installing lights and boxes, but it’s been too cold for him to run wire through the house – he’s waiting for heat! We anticipate hooking up the panel next week if Lower Valley can get us on their schedule, and we’ll have heat shortly after that. The gas fireplace unit has been ordered, and the chimney stone has cured and been uncovered. It looks great!