John & Marlene –

The drywall crew is texturing this week, and should be close to being done by tomorrow.  The tile sub. has started to prep. the showers and tub areas, and will start building the shower curbs tomorrow.  The HVAC crew set the fireplace today, and raising it up a foot really helps – it was just too low when it was flush with the floor.  The wood flooring is ordered and should arrive in about 4 weeks.  The interior doors are nearing completion at the shop, and they just need the hardware info. to complete the job.  I will be checking dimensions and appliance fit on the cabinet shop drawings, and I hope everyone will review the drawings as soon as possible so that we can get them into production.  – – – Dave