John & Marlene –

The roofers have dried-in the roof, so the carpenters are installing windows and starting on the soffit.  The electricians have installed the electrical service equipment on the outside of the garage, and we will be able to switch from our temporary power once the ground thaws and we can run the last few feet of conduit up to the service.  All of the framing changes have been made, and the trades will be starting rough-in soon.  – – Dave