John & Marlene –

All of the windows, except one, are installed.  The window in the Master Closet came in too tall, and the replacement will be here on the 25th.  The carpenters are continuing with the soffit work, and have started to trim the exterior of the windows, and install flashing above the stone veneer locations, in preparation for starting the siding next week.  The plumber, electrician, and HVAC subs. will start their rough-in over the next few weeks, with the electrician getting started next week.  Even though the weather hasn’t warmed up much, the house is much more comfortable with all of the openings covered – not the wind tunnel it was before.  The snow is melted off of the site, and it’s fully mud season!  Once it dries out, we will have the excavator grade the site, to fill in the ruts from the forklift.  The mason is also anxious to get started, and we should have enough room to get them going after next week.  – – – Dave