Marozzi-12-6-18

John & Marlene –

Clear and cold this week, which is OK as we are working inside!  Paul is done with the interior casing and some of the baseboard.  He is working on the barn wood paneling in the Jr. Master at the moment.  The painters are working on stain and lacquer on the window and door casing.  The tile is done, except for a few pieces in the Master Bath floor (on order) and the Powder Room floor (also on order).  We should be seeing those final pieces any day now.  The wood flooring started going down this week, and the Living Room is done, and they are moving into the Kitchen/Pantry area.  They will be working tomorrow, and Saturday, to get those areas done ahead of the Kitchen cabinets arriving on Monday.  – – – Dave