The concrete sub mobilized to the site Monday morning and began laying and tying rebar and building forms for the footings. OnSight was able to do partial staking of the building corners on Tuesday, and completed the remaining corners Wednesday morning with the construction drawings in hand. The framer came to install some holddowns for the structural shear walls, and all the forms and rebar were complete Thursday evening. The first inspection was passed Friday morning, and concrete trucks arrived soon after. The crew will continue next week with forming the concrete foundation walls, which we hope to pour by the end of next week.