Marino Farrell 12/14/18

The sheetrock crew wrapped up their install this week of the ceiling and most of the upper walls. They will return to hang the lower walls once the flooring, doors, baseboard, and sills are installed. The electrician returned and put down the floor heat wire in the master bath, and the tile guys finished laying the floor tile in the master bathroom that same day. They also completed all the shower pans and shower floor pebble tile. We took delivery of the pre-stained siding on Monday, along with the poplar trim package (sills and baseboard). The flooring delivery should happen next week, and Kevin will begin installing soon after that.