Marino Farrell 11/16/18

The insulators finished up foam in the crawlspace this week, and did a big clean up. The garage entry door was delivered Wednesday and the carpenters returned to install it Thursday; they did a little more miscellaneous framing work to prep us for sheetrock. We hope to have the sheetrock delivered next week, but it may be the following week due to Thanksgiving. The sheetrock crew will start hanging the ceilings and upper walls as soon as we have the material delivered. The plumber is on site completing the gas lines and shower valves, which will prep us for our final rough-in and insulation inspection tomorrow. Wade Metalworks has been working on the metal soffit and fascia, and hopes to be done before Thanksgiving as well. The oak flooring is at the Valley Hardwoods warehouse acclimatizing, and can be delivered with a week’s notice, so we’re on track with flooring. We also expect delivery of the exterior siding and interior base/sill material beginning of December.