Winter descended on the valley this week. Monday brought wet snow to the valley floor and cold temperatures that persisted through the week. We passed the electrical rough-in inspection first thing Monday morning, which paved the way to passing our final framing, plumbing, and mechanical inspection on Thursday. We are now ready for insulation first thing next week. The framers returned for a day of work to wrap up some final framing details and box in some of the duct work. Roberts Concrete prepped and poured the garage slab Wednesday morning; once it is cured we will cover it to protect it for the rest of construction. The roofers worked Monday but had to pull off for a couple days because of high winds – the metal panels were almost going airborne when they called it quits, but they’re back on site making good progress today. Woodland Cabinetry and Quality Woodworking (doors) both made site visits this week for field measurements, and we should see shop drawings sometime later this month.

 