Marino Farrell 10/26/18

Busy week at the site, with a team of 5 to 6 electricians working to finish up rough-in this week. All of the wires, including low voltage for the Lutron system, shades, and thermostats, have been pulled. The plumber is wrapping up running all the water lines and installing rough-in valves for the plumbing fixtures, and the HVAC crew will have all supply and return air ducting complete early next week. The roofers returned to start installing the metal panels, so the roof should be complete in a couple weeks – then we’ll see the crew finish off the metal soffit and fascia. Weather has still been quite mild, but a chill is creeping back in and we should see the snow level start to drop down to the valley again next week. Just in time for insulation!

 

Custom Wordpress Web Design