Harris 7/23/15

With the building permit in hand we were able to pour the concrete yesterday afternoon for the foundation footers. The crew has been out there today stripping the forms. We have the surveyor scheduled for Monday to set reference points on the footers so we can begin forming the concrete foundation walls. Lower Valley hooked up a temporary panel to the transformer on the west side of the property, and I met with the electrician on site to go over the new location of the electrical closet.

The first part of the steel package is ordered and will be delivered next week in time for the foundation pour. We also have the floor and crawlspace framing package ordered and ready to be delivered as soon as the concrete work is complete. Afternoon thunderstorms continue to prevail, but so far they have not slowed progress.