Harris 6/2/16

There was a lot of activity this week. The flooring has been installed, and they’re working on the stairs, and sanding and finishing. The Master terrace is underway, and the bollard lights are installed on the north terrace in preparation for the terrace stone on that side. Trim is coming along, and should wrap up next week. We have the painter scheduled to start staining and lacquer on the trim, second coat on the walls, and to continue exterior touchup. The exterior railings were delivered, as was the propane tank.

 

 