The painters spent the week spraying the primer and first coat throughout the house. They also finished the two coats of paint on the ceiling. They will return Monday to continue touchup on the exterior, and to stain the front and garage doors. The tile workers were on site all week doing their prep and layout. They have a good start on both the upstairs bathroom floor and the shared bathroom floor. The excavator finished the water and sewer line, and got a good start on rough grading and terrace prep. The plumber was then able to hook up the water to the house and install the water meter. The interior door package is expected next Thursday with the rest of the trim package not far behind that. The carpenters will be back on Monday to do some final framing and sheeting adds to the living room fire place wall and will then move on to hanging doors.