The weather this week was a bit iffy with some rain, little snow flurries and some sun.  The fascia is complete and the house is dried in.  The carpenters have started trimming out the windows as you can see from the pictures.  Tomorrow the insulators are scheduled to spray the 1″ layer of foam.

Monday will be the start of rough in for plumbing, electrical and HVAC.