The windows arrived today!  Well, most of them.  The rest should arrive next week.  The crew will start installing them on Monday.  The carpenters were back on the north dormer this week, installing soffit and siding, and building the cold roof vent below the dormer, to vent the existing roof that runs from the dormer down to the front entry.  They also framed as much of the upper level exterior deck as they could, working around the masons and the chimney.  The chimney is up to deck height, and passed inspection today, so they will grout tomorrow, and then continue on to the top.  I’m in the process of ordering the interior doors, and should have shop drawings next week for review.  I’ve also got the interior trim takeoffs done, and will be getting quotes on that next week.  Hoping that alder comes down in price, as the framing material has.  – – -Dave