The nice weather continues, and we deserve it!  The carpenters are working on finishing up the exterior, building the doors for the electrical enclosure and the crawlspace access, installing the redwood decking, and trimming out the garage doors.  The masons are setting the stone ledge on the back of the house, the rest of the exterior stone work is done.  The insulator has taken over the inside of the house, spraying foam in the exterior walls, and they also did the Screened Porch walls and roof yesterday.  The rest of the timbers are ordered for the Living Room and Master Bedroom ceilings, and I ordered a bit more of the beveled siding to finish up the exterior, and that should be here next week.  – – – Dave