John & Marlene –

The carpenters are closing in on finishing the exterior siding and trim.  During thunderstorms this week, they moved inside to finish installing blocking and drywall nailers.  The topping slab has been poured on the main level, and next week, after it has cured for awhile, we will install the plywood over it.  The electricians, plumbers, and HVAC crew are finishing their rough-in, and should be ready for the insulation to start next Friday.  The security crew will come in next week to pull their wires ahead of the insulation.  The masons have been moving along on the stone veneer, and should be done in a few weeks, at most.  We will hopefully have the interior elevations soon, so we can price the cabinets and get them in production.  Have a great holiday weekend!   – – – Dave