John & Marlene –

Winter got serious this week, with lots of snow and wind.  The tile sub. sealed the Master Bath Floor, and is done except for sealing a few areas that the painters have masked off.  The painters are finishing the last coat of lacquer upstairs, and are putting the final coat on the drywall upstairs also.  Now that the railing design is approved, Paul has set the post brackets on the stairway, and is proceeding with the finish woodwork on the stairs.  He will finish next week, and then Kevin will sand and stain the wood floors, and get the first 2 coats of finish applied.  Neal templated for the countertops, and we should see some countertops going in next week.  The carpet supplier/installer, Jeff Edwards, measured for carpet, and we should have a price from him next week.  The rest of the cabinets showed up last night, and are stocked in the Garage.  Hopefully the installers start today, as the cabinets take up all of the space in the Garage!  – – – Dave