Marino Farrell 9/21/18

This week the framing crew continued with the window install. The remaining sliding doors from Pella arrived on Wednesday, and had to be assembled. They should have the last of the windows installed early next week. The plywood backing for the metal soffit is also complete, as well as blocking for the siding. The crew hopes to wrap up remaining miscellaneous framing – attic accesses, shower niches, fireplace walls, dropped soffits, etc. – next week in preparation for rough in.

 