Marino Farrell 8/24/18

The framing crew continued this week with cooler temps, some rain, and lots of smoke. They installed the posts at the front entry and several of the major beams that carry the roof load. They finished the wall sheathing and have been taking care of additional blocking, holddowns, and bracing now that the trusses are installed. They have prepped the layout for the deck framing which they’ll work on once the north porch roof is complete. The electrician tied in his conduit to the well cap and ran wire into the crawlspace, then the well was backfilled for the final time.