The only parts of the house left standing are the garage and bathroom 2! Rusty and team have demo’ed the roof, and almost all of the interior and exterior walls. The waste is being hauled off in dumptrucks. Power’s Excavation has finished backfilling the foundation walls and have prepped the garage and front walkway for slabs. They also started digging for the new water line, and ended up doing some repairs on the curbstop for Rafter J. They should finish it up tomorrow. The pony walls in the crawlspace are being framed up and the floor re-sheeted. We’re expecting some more rain tomorrow, and without a roof, we’ll do our best to keep the site tidy and progress moving forward.