Harris 7/29/16

Lots of activity this week. Many subs are back and forth taking care of final details and punch list items. The flooring crew returned on Tuesday to put the final coat of poly on the oak floors. The painters wrapped up some touchup, the tile crew completed remaining caulking and sealing, the electrician installed the house numbers, and the carpenters are taking care of final details. The carpet installers arrived on site yesterday and anticipate completion at the end of today.  The garage firedoor hardware is being modified to fit 3″, and should be installed next week. The handrail for the interior stairway arrives today and should be installed as well. The cleaners will be in the house over the weekend, and we will be ready for final inspection.

 