The masons completed the interior stone work this week and it looks great. The carpenters are working on hanging all the interior doors, and have been eagerly awaiting the arrival of the interior trim. We took delivery of that today – all the window and door trim and baseboard are stocked in the garage. The painter will return Monday to start pre-staining the baseboard, and removing and staining the doors. The tile in the downstairs bathrooms has been grouted, and we’re waiting on a few more specialized pieces to complete the work. We’ll also have the cabinet installers on site Monday – should be a busy week!