John & Marlene –
The painters are working to finish the upstairs, and will be spraying another coat of lacquer on the trim upstairs this weekend. The custom cabinets by Josh Weltman were installed yesterday. The Laundry Room cabinets will be installed by next Wed., and then Neal will template for the granite countertops. The sinks and faucets were delivered today, so that Neal has the sinks to mount when he comes to template next week. The cabinet hardware is due in at Rocky Mountain Hardware early next week, so will pick that up for the installers to install. The floor tile for finishing up the Master Bath should arrive next week. – – – Dave