All structural framing was wrapped up this week. The guys finished the north porch roof framing on Monday, and continue to work on deck framing. They are also starting on plywood on the soffits, siding blocking, door framing, and other miscellaneous items. The Pella window delivery arrived today, and we unloaded all window/door units except for the large three-panel sliders for the great room. The house is Tyvek’ed and the window openings have been flashed, so they will start installing some of the smaller window units this afternoon, and finish up early next week. The roofers were also on site on Wednesday to dry in the roof, so the windows will be protected once installed. Things are moving along nicely, and we’re on track to start electrical, plumbing, and HVAC rough-in in the next week or two.