More rough-in progress this week, with the electricians finishing boxing out 95% of outlets, cans and switches. Karen and I will do a walk-through next week to approve all locations and go over any conflicts/issues. They also installed the electrical panels in the garage, and we are on the schedule with Lower Valley for them to turn on the service to the house next Thursday. The HVAC crew ran most of their duct work as well, and were able to install the living room fireplace and vent pipe. A couple carpenters came back to the site for half a day to do some blocking/heading to accommodate electrical and HVAC layout. Everyone is making great progress despite the weather turning cold, especially in the mornings!