Granite Ranch-1-21-21

Kurt –

Now that we are into the framing, starting to see some good progress.  The roof framing will be done by tomorrow, they are working on the overbuild areas, and the the area where the roof ties into the Residence cabin.  They will have the fascia on by early next week, so I’ve notified the roofer that they can start next Wednesday.  I’m setting up the window delivery for the first week of February, and also having the electricians starting then.  The painter came out to the site yesterday, and is starting today to stain the logs.  Due to some of the tight spaces between the logs and the frame walls, we thought it would be easier for them to stain the logs before we had the walls framed and sheathed.  – – – Dave

Custom Wordpress Web Design