Morse-3-24-16

Bob & Stacey –

The first container of windows arrived yesterday, and we will start setting windows tomorrow or Monday.  The installation hardware is in the second container, so Zola is Fed-Ex’ing us some hardware to get us going, and that should arrive tomorrow.  The crew has been prepping all of the window openings, working on the timber frame at the Family Room Terrace, finishing up the framing and sheathing of the Family Room roof, and continuing with the interior wall framing.  The Isokern fireplaces arrived in town, and will be shipped up to the site next week.  The fascia arrived today, so we will start on the fascia/soffit on the roof in the next few days.  We have closed up the window and door openings on the south side of the house, and have the electric heaters going in the basement – it’s almost dried out.  Mud season continues, with snow and rain still in the forecast.  Supposed to be clear this weekend, hopefully it is clear next week also.   – – Dave