Marino Farrell 5/9/19

The excavators have been on site this week doing the final grading around the house. They also re-shaped the berm with all the remaining material on site. We are now ready for the landscapers to begin some preliminary work – installing irrigation, drain rock, metal edging – and Steve O’Brien should mobilize tomorrow. The carpenters have made a bit more progress on the guest wing decks, and will continue around to the living room and master. Inside, the drywall guys are finishing up the last of their tape and mud, and will begin adding the light texture to the walls tomorrow. Next week we will juggle painting and cabinet install in select areas, so lots to look forward to!